Vulcan Logo
HEM:EPC: assumptions and limits

HEM:EPC: assumptions and limits

Last updated: 26/11/2026

Where Vulcan makes an assumption to run HEM:EPC, and the limits of HEM:EPC that Vulcan cannot remove. A run notice is a message Vulcan shows with the results of a run.

About these results

  • Not an EPC. A HEM:EPC result cannot be lodged. Use it to compare options and to learn the method.
  • Provisional. The rating formula and bands, the 2024 fuel prices and the product list are interim samples, so results will change when the final rating method is published.
  • Weather and region. HEM:EPC uses one weather file, for Bedford, for every dwelling, and it affects every result. The postcode gives only the nation, which sets the age bands.
  • Filled values. Each value Vulcan fills shows as "(default)" or "from occupancy" in the form, in a run notice, and in the EPC Report under "How Vulcan entered this model". Type a value to replace it.

Values Vulcan fills when you give none

  • Combi daily hot water. From the occupancy.
  • Primary pipework. With no pipe drawn, Vulcan uses a default pipe from the cylinder to its heat source. Draw the pipe to give its real length, size and insulation.
  • Studio. Runs as one bedroom.
  • Dwelling length, width, ground floor area and storeys. From the drawing.
  • Heat pump upper flow temperature. 60 °C on its hot water coil and 65 °C on its heating circuit.
  • Mixed emitters on one circuit. The first emitter sets the design flow temperature.
  • Cylinder coil. Flow rate 10 L/min, heat transfer rate 300 W/K.
  • Cylinder heater thermostat position. 0.33 of the cylinder's height for an immersion heater, and 0.5 for a coil or any other heater except solar thermal; a heater placed higher puts its thermostat at its own height, as the thermostat cannot sit below its heater.
  • New-build MVHR duct size. The size category nearest the drawn ducts.
  • Solar thermal (new build). Mass flow rate 0.02 kg/s for each m² of collector. The solar loop heat loss comes from the collector product and its area. A value you type is kept.

How Vulcan enters the drawing

  • Ground floor U-value. When a ground floor has a construction resistance and no U-value, Vulcan works out each part's U-value from the area and exposed perimeter of the storey's whole ground floor, and from that part's own construction. A U-value you type is kept. A file saved by an earlier version of Vulcan keeps its old exposed perimeter until you open and save it. That gives a slightly higher U-value, so open and save old files before a batch run.

New build only

These apply only to a new build. Vulcan enters a new build as it does for HEM:FHS.

  • Heated basement. Sent as one ground floor element that includes the walls below ground.
  • Storey height. The height you type in the floor picker, else the height of the walls under the floor above, else the storey's tallest wall.
  • Zone floor area and volume. Vulcan works them out from the drawing. Each part of a storey counts at the mean height of its own walls, and the floor of a bay above the ground floor or of a conservatory open to the dwelling counts. A floor area or height you type is kept.
  • Conservatory. Draw a conservatory only if it is open to the home and heated. A separated conservatory is not part of the dwelling, so don't draw it. Vulcan keeps the wall between the conservatory and the home as an internal wall, so don't draw that wall again.
  • Distant shading. Angles are measured from the centre of the floor area, distance from the closest external wall.
  • Bay and conservatory floors. Vulcan enters a bay's ground floor as part of the ground floor it extends, with that floor's construction. A bay floor with a different construction is entered as a floor of its own, or stops the run if it is smaller than 5 m². A conservatory floor smaller than 5 m² also stops the run: make the conservatory larger.

Not in HEM:EPC yet

If the dwelling has one of these, Vulcan says so on the element and the HEM:EPC run does not go ahead, unless the line says what to do instead.

  • Oil heating. There is no oil fuel to choose yet.
  • Back boilers, air-to-air heat pumps and electric warm air. HEM:EPC cannot run them yet. Vulcan shows them as not available where you choose the heating, with the reason.
  • Heating controls of ecodesign class V to VIII. They have no default settings. Enter them on the heating controls, or choose another class.
  • Curtains and blinds. No product exists yet, and HEM:EPC cannot take one yet. Vulcan shows the window treatment as not available on a new build.
  • Smart air bricks. The HEM Database lists no smart air brick product, so Vulcan cannot give one. HEM:EPC does not look up the product. Vulcan shows the smart air brick as not available on a new build's suspended floor.
  • Combustion appliances. HEM:EPC has no input for them. Enter a fire or stove as a room heater whose flue names a passive duct.
  • Elements next to an unconditioned zone, on an existing building. HEM:EPC has no such element for an existing building. Draw the element next to an unheated space, with that space's thermal resistance.
  • Unconditioned zones by the direct method. HEM:EPC cannot run them yet. Use the calculated method and give the zone's elements.
  • A hot-water-only heat pump in a smart hot water tank or a primary thermal store. HEM:EPC cannot run it yet. A storage tank can take the heat pump.
  • Weather compensation on heating controls of class I, IV, V or VIII, on an existing building. HEM:EPC does not take a weather compensation curve for these classes. Vulcan shows the curve fields as not available for them.
  • Stucco or aggregate paint on a park home wall. HEM:EPC rejects every finish of this surface material. Describe the wall's outside surface by its colour.
  • Fan coils, on an existing building. HEM:EPC cannot run them yet: the existing-building input has no number of units, and the calculation needs it. Vulcan shows the fan coil as not available there.

Existing building only

These apply only to an existing building. A new build takes the full inputs, so none of them applies to it.

  • No air test. Give the open fireplaces, the double glazing period and, for a flat, the corridor in Global Settings > Air test. HEM:EPC estimates the rest with an interim method.
  • Loft insulation location. A new model starts it as unknown, and a saved model with it blank opens as unknown; HEM:EPC then takes the insulation from the dwelling's age band. Set the location and thickness from the survey.
  • Radiator circuit thermal mass. 0.055946206 kWh/K.
  • Uninsulated floor. Runs as uninsulated. The result is unchanged.
  • XPS floor edge insulation. Conductivity 0.036 W/m·K.
  • Suspended floor wind shelter. Follows Shelter in Global Settings.
  • Flat given only its storey. Vulcan works out its height above ground from the storey.
  • Stone walls (granite, sandstone, limestone). Vulcan fixes a fault that stopped these runs. The method's own values are used unchanged.
  • Hipped, mansard and gambrel roofs, and hip dormers. Entered as dual pitch, with a run notice. A conservatory roof of another shape is entered as a lean-to or a dual pitch.
  • Bay shape, roof and side windows. Vulcan enters a bow bay as a canted bay, its middle facet the front and the chords to it the sides. It enters a pitched bay roof as one 35° slope. It does not count the wall between a bay roof and a cold loft. It enters bay or dormer side windows that differ in size, or a bay side window on one side only, as one size for both sides. Each gives a run notice.
  • Room in the roof under a hipped end. Vulcan enters the hip end as a gable wall. If each knee wall under the hip has a U-value or layers, Vulcan sets the gable's U-value so that it loses the same heat as the knee walls, with a run notice. If not, the gable takes the knee wall's construction and age band, and a run notice gives the difference in wall area. With no knee wall under the hip, Vulcan enters a party wall that loses no heat. A party wall under the hip stops the run until you draw a gable there or change that wall.
  • Vaulted ceiling. Entered as a loft roof. Give the slopes a U-value.
  • Building parts. A part over different floors is split, one part per floor. A part above the ground floor with no floor drawn under it has its floor over outside air.
  • Ceiling height. The average height of the storey's walls, less the floor between storeys.
  • Bay above the ground floor. HEM:EPC counts a bay's floor only on the ground storey, so the floor of an upper bay is left out of the floor area. Allow for it when you compare with a floor area you measured.
  • Fan on a roof or in a roof window. Vulcan enters it in an outside wall of the room below it.
  • Window reveals. HEM:EPC does not take a reveal on an existing building, so Vulcan leaves it out and names the window in a run notice.
  • Insulated door. With no documented U-value, Vulcan treats it as uninsulated and takes the age-band U-value.
  • Some shapes are not in HEM:EPC yet. A conservatory wall or roof with no glazing, a bay with unequal sides, and a basement wall with a window or door. The run does not go ahead until you change them.
  • Exposed area. HEM:EPC uses the same exposed area for every dwelling, so thermal bridge and air leakage losses are too high for a small dwelling and too low for a large one.
  • Floor between storeys. HEM:EPC leaves it out of the wall area, so wall heat loss is too low.
  • Internal walls. HEM:EPC sets the internal wall mass from the floor area, so it does not use the internal walls you draw. A run notice counts them. Overheating still uses them.
  • Door in a conservatory wall. HEM:EPC takes no solid door in a conservatory wall, so Vulcan leaves the door out, with a run notice. Make the conservatory's Wall glazing larger to include the glass of a glazed door.
  • Lighting and thermal bridges. HEM:EPC works them out for an existing building, so Vulcan does not offer them there.

See also

These notes match HEM:EPC 0.13.2. We update them with each Vulcan release. To report a wrong default, email support@usevulcan.app.

Still stuck?

← Back to Documentation